In the Zone - Week 13

In the Zone - Week 13

August 12, 2016

And the WALLS came tumbling down...well maybe only two.

And it took a bunch of muscle and man-power.

BANG. BANG. BANG.

Office addition update: The outside of the building is on stand still but the inside is looking a tad different.  Don't miss the pics of the door frames for each office, they are leaning against building and the turbo truck bringing them inside. Two new hallways between the current office and new office were started this week by knocking out a 5 foot section of cement brick wall plus they added a support I-beam at the top - see pics.

Warehouse addition update: The rainy weather did halt progress a bit on this project.  The cement walls were planned for Wednesday, then Thursday, then Friday. None of them worked out, we will look for the walls next week, hopefully.